Boggo Road, brisbane, cross river rail, queensland, tunnelling,
1917 views
With tunnelling complete for Queensland’s largest infrastructure project, all four underground station structures are beginning to emerge with installations.
With tunnelling complete, crews are now focused on the next exciting phase of construction – the stations taking shape.
Underground stations
Cross River Rail’s four new underground stations are the centrepiece of Queensland’s largest infrastructure project and are being built in convenient locations in and around the CBD. At the project’s southernmost underground station – Boggo Road – installation of formwork, reinforcement and concreting is continuing, and the station structure is beginning to emerge.
Crews have also begun lifting huge concrete beams, precast at Wagners in Wacol, into the station box, which will be used to build the station’s future mezzanine level. Mezzanine fit-out has also been a focus at Woolloongabba, where 180 concrete beams weighing up to 70 tonnes are installed in the station cavern with millimetre accuracy using a world-first construction technique.
You can see the beam installation process at Woolloongabba on Facebook.
Elsewhere at Woolloongabba, the station’s services building – built out of the 33-metre-deep station box – has “topped out” and is now clearly visible from street level.
On the north side of the river, works are progressing well on the future Albert Street station – a site that boasts the deepest hole ever excavated in Brisbane, at 50 metres deep. Crews are working on the station buildings and two future entrances, with concreting and steel fixing becoming a focus as the structures continue to rise.
Rounding out the underground quartet is Roma Street, where works on the services and future station buildings are progressing well. A total of 25 concrete pours throughout 2022 will also take place to line the Roma Street cavern, with 19 already taking place.
Aboveground stations
But there is much more to Cross River Rail than underground tunnels and stations. Aboveground, they are completely rebuilding eight Brisbane stations and delivering three new ones on the Gold Coast.
As part of the project, the Exhibition station will welcome year-round train services – and works to rebuild the station are well underway. The old station building has been demolished, and the installation of masts and foundations for overhead electrical wires is progressing.
Early works are underway at Dutton Park, where the station is prepared for significant construction. The six stations between Fairfield and Salisbury, just south of Cross River Rail’s twin tunnels, are also being rebuilt as part of the project, with a third platform and significant accessibility upgrades being delivered.
The first southside station to be upgraded, Yeronga, reopened to passengers earlier in the year, and the complete rebuild will be finished in late 2022.
Finishing touches are being put on the Fairfield Road overpass, and lift car installation and platform two and three construction is continuing. Similar works are currently taking place at Fairfield station.
Reopening later this year, crews are building Fairfield’s new platforms and installing canopies to provide shade for passengers waiting at the station. Fairfield’s timber overpass and stairs will also be removed next month, allowing construction of the new fully accessible overpass to progress.
Rocklea station, the third southside station to be rebuilt, closed recently, and is scheduled to reopen in late 2023. Early next month, 270 metres of the track will be lowered at Rocklea, ensuring the platform surface is step-free.
The other three stations – Salisbury, Moorooka and Yeerongpilly – will be closed and upgraded on a rolling schedule, all set to reopen in line with Cross River Rail in 2025.
Procurement activities for the three Gold Coast stations being delivered by Cross River Rail – Pimpama, Hope Island and Merrimac – are well underway, while early works at Pimpama are underway.
Source: © Cross River Rail Delivery Authority 2021 | © The State of Queensland 2022
Image source: © Cross River Rail Delivery Authority 2021 | © The State of Queensland 2022
Cross River Rail – October 2024 update
65 views
In a huge milestone for the Cross River Rail project, a train has entered one of the project’s twin tunnels.
Completion date announced for Gympie Bypass
330 views
Completion of the $1.162 billion Gympie Bypass is just weeks away, with confirmation that works are on track to be finished in October 2024.