Balfour Beatty VINCI, HS2, UK,
716 views
HS2 has completed the first 920-tonne deck span on the first precast viaduct being built at Delta Junction, as works ramps up on the network of 13 viaducts in North Warwickshire, UK.
HS2 has completed the first 920-tonne deck span on the first precast segmental viaduct being built at the Delta Junction, signalling a construction milestone as work ramps up on the complex network of 13 viaducts in North Warwickshire.
HS2’s Delta Junction is a triangular section of line, enabling trains to travel between London and Birmingham, Birmingham and Manchester, and direct between London and Manchester without stopping at Birmingham. It is made up of embankments, cuttings and a total of 13 viaducts taking high speed tracks over motorways, local roads, existing rail lines, rivers and floodplains. The viaducts include 6 precast segmental viaducts, 4 composite viaducts and 3 low viaducts.
The River Tame West Viaduct is a precast segmental viaduct at the northern tip of the Delta Junction, crossing the River Tame near Water Orton, and joins the Curdworth Box which will take high speed trains over the existing Birmingham to Derby railway.
In this complicated section of the Delta Junction, there are six tracks of the railway running alongside each other as they join the southern end of the Curdworth Box. The River Tame West Viaduct carries three tracks, the River Tame East Viaduct carries one track and the Water Orton Viaducts carry two tracks.
To the south, the 1,400 metre Water Orton No.1 Viaduct and 1,300 metre Water Orton No.2 Viaduct curve towards Birmingham allowing trains to travel to and from Curzon Street Station. The other four lines – on the River Tame Viaducts, join on to the HS2 mainline to Interchange Station and on to London.
“This is a great moment for the Delta Junction team, as construction gets into full swing on this linchpin section of HS2. Building this triangular network of 13 viaducts is a huge feat of engineering, with a total of 10km of HS2 tracks crossing a network of motorways, local roads, railways and rivers to enable high speed trains to travel between London, Birmingham and the North,” says HS2 Senior Project Manager for Delta Junction Sam Hinkley.
Construction of the viaduct piers started earlier this year, with deck construction now well underway. The 16 concrete segments for the first span were lifted by crane, placed one-by-one onto two 42 metre truss beams, moved into place with a skidding trolley, and secured by temporary and then permanent post-tensioning techniques.
The span, weighing 920 tonnes, was then jacked up and the truss was moved onto the adjacent abutment and pier, so the process can start again on the next span.
The three initial spans, all from the same abutment and next to each other, will be completed by Spring next year. The further spans will be constructed using temporary staying masts, swivel cranes, and temporary and permanent post-tensioning techniques.
The project is being delivered by HS2’s main works contractor for the West Midlands, Balfour Beatty VINCI (BBV) who are constructing 90km of HS2 between Long Itchington in Warwickshire to the centre of Birmingham and Staffordshire.
“It’s an exciting moment to see the River Tame West Viaduct starting to take shape, now we’ve successfully completed the first deck span. It’s the clearest sign yet of the huge progress we’re making on this complex network of viaducts, known as the Delta Junction,” says Balfour Beatty VINCI Section Manager Nicolas Gallone.
“Construction of this iconic stretch of the route is set to ramp up further over the coming weeks and months, as we continue assembly of more deck spans along this 472-metre-long viaduct, and the adjacent viaducts that run alongside it,” says Balfour Beatty VINCI Section Manager Nicolas Gallone.
The delivery of all the design requirements for the BBV and HS2 works between London and Birmingham is through a Mott MacDonald and SYSTRA Design Joint Venture (MMSDJV). As well as bringing a wealth of in-house design knowledge and expertise, Mott MacDonald and SYSTRA are utilising a local supply chain the length and breadth of the Midlands.
“This is a fantastic milestone moment for the project team. Seeing the first span in place is the realisation of the collaborative, innovative approach to design that the Mott MacDonald and SYSTRA Design Joint Venture has embraced, which will ultimately help high speed trains to run from Old Oak Common to Birmingham,” says MMSDJV Project Director Ian Johnson.
A total of 153 piers will be built for the viaducts in the triangle-shaped Delta Junction, with 15 completed already. At total of 2,762 viaduct segments are being made at HS2’s outdoor factory near Lea Marston using a ‘match-casting’ technique. This involves casting each segment against the following segment in a production line, creating a seamless viaduct deck when installed.
Each segment is uniquely precise and adjustable by minimal tolerances. This approach – where each segment is poured against the previous one – ensures the whole geometry fits perfectly when assembled on site.
The layout of the Delta Junction triangle means the railway from London curves west on a spur towards Birmingham Curzon Street Station. As trains come out of Birmingham, the line heads north to meet the main HS2 line, which will then connect to the West Coast Mainline to Manchester. The third side of the triangle allows trains to run between London and Manchester without stopping at Birmingham.
Delta Junction Viaducts
- 6 precast segmental viaducts (River Tame East and West; Water Orton 1 and 2; Coleshill East and West). Segmental viaducts have standard spans of 45 metres with decks built off concrete precast segments which are prefabricated at HS2’s Kingsbury Precast Yard at Lea Marston.
- 4 composite viaducts (M42/M6 Link Road East and West; River Cole East and West). Composite viaducts have standard spans of more than 45 metres with their decks built off weathered steel boxes or beams, with a concrete deck on top.
- 3 low viaducts (M42 Coleshill North and South; Watton House). Low viaducts have standard spans of 25 metres with their decks built off standard concrete precast beams, with a concrete deck on top.
Source: © High Speed Two Ltd 2024
Image Source: © High Speed Two Ltd 2024
‘Black hole’ Britain must learn lessons from HS2
113 views
The Institution of Civil Engineers (ICE) has published a report, The cancellation of HS2 Northern’s leg – learning lessons.
Skanska completes enabling works at London Euston station
224 views
Skanska along with the supply chain have successfully completed a huge programme of enabling works at Euston station.