cross river rail, Pimpama station,
540 views
Recent track closures allowed for critical Cross River Rail works to take place across Brisbane’s south and the Gold Coast, including the installation of a huge new pedestrian bridge at Pimpama.
The 45-tonne bridge was lifted into place over the rail corridor by a specialised 850-tonne crane, as significant progress continues at the site. Check out the milestone moment below:
More than 400 workers were busy completing vital work over the Easter holiday period, which included hundreds of metres of new track laid and kilometres of signalling and fibre optic cables installed across the project.
These works could not have been completed safely or efficiently while trains were running.
Final design released for Cross River Rail’s Pimpama Station
Project Spotlight: Cross River Rail
Cross River Rail Delivery Authority Graeme Newton said the track closures were essential to the transformational project and thanked the community for its patience.
“The track closures have allowed crews to undertake an incredible amount of work safely and efficiently in the rail corridor,” Mr Newton said.
In the rail corridor south of the new Cross River Rail tunnels, crews laid approximately 700 metres of new track, alongside the installation of six kilometres of new signalling cable, 11.2 kilometres of fibre optic cables and five new signals.
About 10 tonnes of steel was installed at Yeerongpilly, as well as the pouring of 250 cubic metres of concrete and the removal of 1200 tonnes of material.
At Salisbury station, about 100 metres of a new stormwater line was installed between train tracks, precast walls were lifted into place to form one of the station’s new platforms, and piling works were completed ahead of construction of a new pedestrian overpass and lift towers.
Preparation works for new Cross River Rail track was carried out at Dutton Park, while 160-metres of drainage was installed as work continued on the new station’s canopy and platforms.
Station fitout works were completed at Rocklea, which included the installation of water and electrical services and the construction of a new station fence.
Image source: Cross River Rail
Source: Queensland Government, © Cross River Rail Delivery Authority 2024
Cross River Rail – October 2024 update
131 views
In a huge milestone for the Cross River Rail project, a train has entered one of the project’s twin tunnels.
Cross River Rail: Albert Street transformation begins
447 views
Cross River Rail: Works have begun on the first part of the Albert Street ‘green spine’, marking an exciting change to the heart of Brisbane’s CBD.