HS2: Half of Chiltern tunnel cross-passage mining complete

HS2

Chilterns, HS2, Tunnel, UK,

809 views

HS2 reaches a milestone for the Chiltern tunnel, with mining completed for 19 out of 38 underground connections between the northbound and southbound tunnels.

The construction of HS2’s longest tunnels – stretching for 10 miles under the Chilterns – passed a key milestone this week with mining completed for 19 out of 38 emergency cross-passages linking the northbound and southbound tunnels.

Once complete, the tunnel will carry high speed trains between London and the West Midlands at speeds of up to 200mph (320km/h) freeing up space on the busiest part of the West Coast mainline and improving journeys between Britain’s two largest cities.

The trains will travel through two parallel tunnels linked by short passages for use in emergencies. Unlike the main tunnels, which are being excavated by two giant tunnelling machines – named Florence and Cecilia – these smaller cross-passages are dug using remotely controlled mini-excavators.

An expert team of miners use the excavators to break out of the southbound running tunnel and dig the 15-20 metres to the adjacent northbound tunnel.  As the excavation progresses the ground is supported using a sprayed concrete lining (SCL).

Once the team has completed the SCL lined tunnel, a water-proof membrane is installed followed by a secondary concrete lining constructed by placing concrete behind formwork installed in the cross passage.

“We’re making great progress on the Chiltern tunnel with approaching 9 out of 10 miles complete, and our cross-passage teams are catching up fast. Once complete, HS2 will dramatically improve journeys between London and the West Midlands, unlock tens of thousands of new homes and free up space on the busiest part of the West Coast Main Line,” says HS2 Ltd Project Manager Aaron Harrison.

 “While invisible to the travelling public, these hidden passages have a key role in providing a safe operational railway so it’s great to see such good progress,” says HS2 Ltd Project Manager Aaron Harrison.

The Chiltern tunnel is being delivered by HS2’s main works contractor, Align – a joint venture formed of Bouygues Travaux Publics, Sir Robert McAlpine, and VolkerFitzpatrick – which is also responsible for the nearby Colne Valley Viaduct, which also reached the halfway point last week.

“I am delighted with the progress made by our cross-passage team, working in close cooperation with our supply chain partners. In particular I would like to acknowledge the contribution from KVJV who is responsible for the ground treatment, specialist contractor Euro Diamond Drilling and waterproofing specialist Renesco,” says Align Underground Construction Director Didier Jacques.

Once the cross-passages are complete, they are temporarily sealed for fire safety reasons before permanent safety doors can be installed at either end. These are being manufactured by Bolton-based Booth Industries who won the contract to provide more than 300 units for all the tunnels between London and Birmingham.

The win allowed Booth Industries to establish a new facility in the town and create up to 50 jobs over the next 10 years. The sliding doors have been subjected to rigorous fire and fatigue testing to take account of the high train speeds, associated pressures and frequency of the trains. 

Each running tunnel has an emergency walkway that allows passengers to safely evacuate the train and walk through the cross passages into the other tunnel where they can be rescued on a passenger train.  Access for emergency services is from either the portal or one of the five ventilation/emergency access shafts. An additional 5 short tunnels known as ‘adits’, that connect the shafts to the running tunnels, are also under construction by the team with the mining on two of the adits already complete.  

Florence and Cecilia are expected to breakthrough at the north portal early next year.

Source: © High Speed Two Ltd 2023

Image Source: © High Speed Two Ltd 2023

^ Back to top