HS2’s Colne Valley Viaduct crosses UK’s Grand Union Canal

HS2

Colne Valley Viaduct, HS2, railway, UK,

608 views

HS2 reveals the progress of HS2’s Colne Valley Viaduct after 755 of 1000 deck segments were installed to span the Grand Union Canal near Denham, UK.

HS2 has reveled the recently-completed section of HS2’s Colne Valley Viaduct after deck segments were laid to span the Grand Union Canal near Denham.

They juxtapose the new 140-mile high speed London-Birmingham railway against the eighteenth century’s solution to connecting Britain’s two largest cities.

Both were built under powers granted by Act of Parliament; arrive in the Birmingham district of Digbeth; and with similar lengths – HS2, 140miles; the canal, 137 miles – were two of the largest civil engineering endeavours of their time.

The two differ dramatically in other respects. Compared to the sedate progress of canal boats high speed trains will travel across the 2.1mile viaduct at speeds of up to 200mph, completing the journey between the capital and Britain’s second city in just 49mins. 

Uniquely shaped and weighing as much as 140 tonnes , 755 of the viaduct’s 1,000 deck segments have been installed creating 39 spans over land and water for 1.5 miles.

News comes after construction of all the viaduct’s 56 supporting piers was completed in advance of the deck being installed above. 

Once complete, HS2 will provide faster and far more reliable journeys between London and Birmingham, with trains running on conventional lines further north. It will also double rail capacity between the UK’s two biggest cities – relieving the most congested southern part of the West Coast Main Line, creating more capacity for local and freight services.

“I pay tribute to the tremendous dedication and professionalism of the whole team who’ve maintained high standards of safety and quality, working over land and water, come rain or shine to deliver the viaduct’s 56 piers along a 2.1-mile stretch of HS2’s route. Their remarkable achievement will be for all to see across this century and well into the next,” says HS2 Ltd Senior Project Manager Billy Ahluwalia.

“Our work to install the viaduct’s remaining deck segments continues at pace, followed by the installation of the deck edge parapets and noise barriers, before we hand over to Rail Systems for the next major phase of the build programme,” says HS2 Ltd Senior Project Manager Billy Ahluwalia.

Viaduct construction is led by HS2’s main works contractor Align JV – that includes Bouygues Travaux Publics, Sir Robert McAlpine and Volker Fitzpatrick.

“I would like to highlight the huge contribution made by our subcontractor Kilnbridge that ensured all the piers were constructed safely, to the highest quality and in line with the programme. Working over water with complex structures and temporary works, detailed concrete mix designs and with architectural and design constraints, all led to making these works a major challenge of the viaduct construction. I am pleased to say that the integrated working relationship we established with Kilnbridge made delivering this all part of the day job,” Align’s Surface Operations Director Derek Van Rensburg.

Source: © High Speed Two Ltd 2024

Image Sources: © High Speed Two Ltd 2024

^ Back to top