After the extensive damage caused by Cyclone Gabrielle, works begin to repair one of the largest slips on SH5 Napier-Taupō Road in the North Island.
The road was reopened to traffic last week between 7am and 7pm and around the clock from Monday, after initially suffering extensive damage from Cyclone Gabrielle.
An initial slip between Te Pohue and Glengarry made the road impassable until a temporary bypass was constructed well clear of the slip.
Engineers have now completed the design for the long term solution and work began today.
Central North Island Regional Manager of Maintenance and Operations Jaclyn Hankin says initially excavators will be onsite, at the bottom of the site, clearing fallen soil and other material.
“The design will then see the earth built back up, on a 40 degree angle, with rock making up the majority of the material to fill the slope,” says Central North Island Regional Manager of Maintenance and Operations Jaclyn Hankin.
“Plastic geogrid sheeting will also be used in the layering of the bank as retaining material. This is widely used in New Zealand and around the world to stabilise banks for these projects,” says Central North Island Regional Manager of Maintenance and Operations Jaclyn Hankin.
”It is testament to the commitment of our roading crews and engineers, who are working tirelessly to strengthen our roading network that we have reached this milestone” says Central North Island Regional Manager of Maintenance and Operations Jaclyn Hankin.
This site is one of a number of sites still damaged along the route and Waka Kotahi NZ Transport Agency crews are working on a number already.
“Road users will notice changes regularly, as work moves forward at a number of sites. Many areas remain under temporary traffic management and lower speed restrictions. We thank you for your continued patience and understanding during this time,” says Central North Island Regional Manager of Maintenance and Operations Jaclyn Hankin.
Source: © 2023 Waka Kotahi NZ Transport Agency
Construction to begin on next stage of Papakura to Drury
13 views
Construction on the next stage of the SH1 Papakura to Drury project will begin early next month, with the contract awarded to Fulton Hogan
New Zealand releases revised PPP framework
21 views
New Zealand has refined its Public Private Partnership (PPP) framework to enhance the planning, procurement, and delivery of future infrastructure projects.