HS2 Engineers complete a key 40m Colne Valley Viaduct span over Moorhall Road between Denham and Harefield during a three-week road closure.
Tag: HS2
HS2 ‘marathon’ bridge construction completed near Lichfield
1011 views
HS2 has completed a ‘marathon’ construction operation at Streethay near Lichfield, which utilised the latest low-carbon design.
HS2 partners with ‘Women into Construction’ to begin new training programme
1036 views
HS2 partners with ‘Women into Construction’ to launch a new four-week training programme, helping women launch a career in construction.
HS2’s TBM ‘Florence’ and ‘Cecilia’ make significant progress through the Chiltern tunnel
1136 views
HS2 tunnelling machines ‘Florence’ and ‘Cecilia’ passes the fourth ventilation shaft, reaching 75% of the way through the Chiltern tunnel.
HS2’s ‘super-hub’ station at Old Oak Common awarded with ‘Outstanding’ environmental designs
1009 views
HS2’s super-hub station at Old Oak Common has won the ‘Outstanding’ rating for excellence in building design, construction and sustainability.
HS2’s TBM Sushila and Caroline complete first mile of the twin-bored tunnel in London
1052 views
TBM Sushila and Caroline completes the first mile of twin-bored tunnel, installing over 16,000 concrete segment rings in London.
HS2 delivers giant 5600-tonne bridge ahead of schedule
1031 views
HS2’s civil contractor, Balfour Beatty VINCI has delivered a giant 5600-tonne bridge into place in Warwickshire 27 hours ahead of schedule.
Leveraging the United Kingdom’s high speed rail expertise
1029 views
The Hon Catherine King MP travelled to the UK to hear from British partners on lessons learnt from developing and delivering high-speed rail.
HS2 Chief Executive Officer Mark Thurston to step down
1169 views
After six and a half years leading HS2 Ltd, CEO Mark Thurston has announced he will be leaving the organisation in September 2023.
HS2’s Old Oak Common Station reaches a two year construction milestone
1125 views
HS2’s new super-hub landmark, Old Oak Common Station in West London has reached a two year permanent construction milestone.
First steel beams delivered for HS2’s low carbon Wendover Viaduct
1033 views
The 25m steel beams forming the low-carbon structure of HS2’s Wendover Dean Viaduct have been delivered before the start of construction.
HS2 trials automotive design technology to drive down embedded carbon by 10%
1102 views
The automated design technology process designed by Altair Ltd will reduce HS2’s embedded carbon by up to 10% and shorter the design process.