Fulton Hogan and HEB Joint Venture begin construction on Cambridge Road Overbridge

Cambridge-bridge-new-zealand

cambridge road, fulton hogan, HEB joint venture, new zealand, Takitimu North Link,

2119 views

As part of the Government’s New Zealand Upgrade Programme investment in better travel options, the Takitimu North Link project connects Tauranga and Te Puna with a new 6.8km expressway and shared path. It’s all about ensuring people get where they’re going safely.

Waka Kotahi Regional Manager of Infrastructure Delivery, Jo Wilton, says people will notice significant changes across the site since the contractor, the Fulton Hogan and HEB Joint Venture, started work in December 2021.

“It’s exciting to see the work starting on the new overbridge at Cambridge Road this month. This site is of real importance to us. It will be visible to the community, and we’re mindful of our neighbours as work takes place.

“The initial focus across the project site has been on setting up site access and environmental controls, ahead of our first full construction season starting in September, when work ramps up through the drier months to April,” says Waka Kotahi Regional Manager of Infrastructure Delivery, Jo Wilton.

“The Cambridge Road Overbridge will be 100m long and carry one lane of traffic in each direction, with wider shoulders and footpaths on both sides of the road. The bridge will be constructed just west of Cambridge Road, keeping traffic impacts to a minimum in this area. Once built, traffic will use the new bridge, so construction of the new Takitimu North Link road can begin with excavation underneath.

“Piling work is expected to take three months, subject to favourable weather and ground conditions. Once the piling is completed, the bridge beams will be installed, and the concrete deck will be poured,” says Jo Wilton.

There will be a temporary speed limit in place; people are asked to take extra care by following signs and instructions from our traffic management team.

“Further north on the project site has also been a hive of activity, piling work for the Wairoa Road Overbridge and construction of a temporary bridge crossing the Wairoa Awa (River) are both nearing completion.

“The project has more than 200 people working on it; our team is now based in a newly constructed site office at Minden Road, Te Puna. This will be our home while we build the new road,” says Ms Wilton.

More than 50,000 cubic metres of earth have been moved across the project site. This construction season (September to April), around 400,000 cubic metres will be moved, about 13% of the project’s total amount and enough to fill 160 Olympic swimming pools.

The Cambridge Road Overbridge is expected to be completed by late 2023.

Source: © 2022 Waka Kotahi NZ Transport Agency

^ Back to top