TBMs Florence and Cecilia mark 90% progress through the 10-mile Chiltern tunnels

HS2

Chilterns, HS2, TBM, tunnel boring machine, UK,

786 views

HS2’s two giant tunnelling machines Florence and Cecilia have reached the Chesham Road intervention shaft, marking 90% progress on their 10-mile journey under the Chiltern tunnels.

HS2 confirmed that ‘Florence’ and ‘Cecilia’ – the two giant tunnelling machines digging the project’s longest tunnels – have reached the Chesham Road intervention shaft, on track to complete their mammoth 10-mile journey under the Chilterns in 2024.

The enormous 2,000 tonne machines are now 90% of the way through their two-and-a-half-year drive between the M25 and South Heath in Buckinghamshire to create the twin-bore tunnel.

In total, HS2 will require 64 miles of tunnelling, with five Tunnel Boring Machines (TBMs) already in the ground, three more ready to go and another two due to be delivered next year. Once complete, HS2 will help improve connections between London, Birmingham and the North while creating space on the most congested part of the existing West Coast Main Line.

Each Chiltern TBM is a 170m long self-contained underground factory, digging the tunnel, lining it with 56,000 concrete segments to form rings and grouting them into place as it moves forward.

Designed specifically for the geology of the Chilterns, the machines were launched in Summer 2021 from a site near the M25 and have already excavated approximately 2.8 million cubic metres of chalk and flint.

As well as digging and lining the tunnels, engineers have also completed the excavation of four other shafts that will provide ventilation and emergency access near Chalfont St Peter, Chalfont St Giles, Amersham and Little Missenden with work now happening to create the internal structures and the headhouses on the surface.

“Once complete, HS2 will transform journeys between London and the West Midlands and free up space on the busiest part of the West Coast Main Line. We’re making great progress in the Chilterns, with 90% of the tunnel excavation now complete. That’s an incredible engineering achievement and I look forward to the breakthrough, next year,” says HS2 Head of Delivery Mark Clapp.

The 42m deep shaft near Great Missenden – which the TBM has now reached – is largely hidden behind a hedge and line of mature oak trees next to the B485.

A ‘headhouse’ will be built on top of the shaft designed to resemble local farm buildings with new planting to help blend it into the surrounding landscape. The Chesham Road shaft will only be used for emergency access, while the others will also contain ventilation equipment.

The two TBMs are operated by, Align – a joint venture formed of Bouygues Travaux Publics, Sir Robert McAlpine, and VolkerFitzpatrick.

Each machine has a crew of around 15 people, working in shifts and supported by over 100 people on the surface, managing the logistics and maintaining the smooth progress of the tunnelling operation.

“With our first TBM Florence having reached our fifth shaft at Chesham Road and our second TBM Cecilia due to reach the shaft shortly, this a great achievement for not only the tunnelling team, but also the supporting teams on the surface at the South Portal, manufacturing the concrete segments required to line the tunnels and processing the spoil from the tunnels,” says Align’s Underground Construction Director Didifer Jacques.

“We are looking forward to continuing the good progress with the TBMs, which are due to complete their drives early 2024,” says Align’s Underground Construction Director Didifer Jacques.

Approximately 3 million cubic metres of material – mostly chalk and flint – will be excavated during the construction of the tunnels and used for landscaping. Once construction is complete, the temporary buildings at the south portal will be removed and the site landscaped with around 90 hectares of wildlife-rich chalk grassland habitats.

Chalk grassland used to be widespread across the hills of southeast England and are considered habitat of international conservation significance with just 700ha left across the Chilterns.

Alongside the Chiltern tunnels, two TBMs are currently excavating the London tunnels with two more due to launch soon. One TBM is excavating the Bromford tunnel in Birmingham with another ready to go. Two TBMs which will excavate the Euston tunnels are due to be delivered to site in 2024.

Source: © High Speed Two Ltd 2024

Image Source: © High Speed Two Ltd 2024

^ Back to top