new zealand, Transmission Gully,
469 views
An independent review into Te Aranui o Te Rangihaeata – the Transmission Gully motorway – has found that external events, budget, governance and consenting issues, rather than the Public Private Partnership (PPP) model, were among the contributors to the project’s time and cost overruns.
The review echoes conclusions from a prior review completed in 2021 in highlighting significant failings in the accuracy of the project’s initial cost estimate or Affordability Threshold as well as aspects of its earlier stage governance.
The reviewers also said that, given the risks and events that impacted the project (Kaikōura earthquake, weather, COVID-19), there’s no evidence that time and cost outcomes would have been better under a non-PPP procurement/contracting model.
Waka Kotahi and CPBHEB JV in legal dispute over Transmission Gully project
Review into Transmission Gully announced
The review was led by independent expert Steve Richards and overseen by the New Zealand Infrastructure Commission, Te Waihanga. Its executive summary and recommendations were released today alongside some guiding insights for future megaprojects.
Finalisation and release of the review has been delayed because Transmission Gully has not yet been completed to the standard required by the NZ Transport Agency Waka Kotahi (NZTA), and final assessment of the project’s costs and benefits may not be available for some time. Te Waihanga felt it was important to release key findings now so they can be applied immediately to current and proposed projects.
The key findings include:
- While there was room to improve the execution of the PPP, the use of the PPP model was not the root cause of the time and cost overruns
- The builder did not anticipate the complexity of the New Zealand Resource Consenting system and was not able to secure all necessary approvals from the Consenting Authority
- Recurring relationship issues between key parties hampered progress
- Project governance issues, including problems with effective decision-making, were a factor earlier in the project
- The Affordability Threshold was set too low.
Te Waihanga Chief Executive Ross Copland says that infrastructure delivery challenges are wide-ranging, and many things can impact on agreed budgets and schedules. This can erode confidence.
“Decision-makers are losing confidence in the numbers presented to them at business case stage,” he says. “We’ve seen unusually high cost overruns in PPP, alliance and traditional contracts alike so it’s clear the issues run much deeper than selecting the right commercial model.”
The recommendations and findings from the Transmission Gully review endorse a number of recommendations made in the New Zealand Infrastructure Strategy (2022-2052).
“We can also improve our consenting system for both regulators and the regulated when it comes to managing big infrastructure projects. I’d like to see us getting good value across the board – including that consent conditions are proportionate to risk and really do provide environmental benefit.
The case for wholesale reform in how we manage the environmental risks of big projects has never been stronger. Likewise, the focus on project leadership, relationships and good project governance are consistent with findings from previous work by Te Waihanga and we need to act on these recommendations promptly,” says Copland.
He says it is essential the sector work together to learn from past issues to quickly restore confidence in its ability to deliver agreed project outcomes on time and within budget. Copland reports that in a recent study on public infrastructure transparency led by Massey University no completed project had proactively released a post-completion review of their project.
“As any good coach will tell you, high performance requires a team culture of systematically reviewing every performance and embedding the lessons learned. Disclosing the findings of those reviews is essential for building public trust and allowing others to learn. We need to lift our game in this regard.
“We are very grateful to NZTA and the wider project team who shared their insights, lessons and ideas for improving future projects. Thanks also to lead reviewer Steve Richards.”
Source: New Zealand Infrastructure Commission
Construction to begin on next stage of Papakura to Drury
14 views
Construction on the next stage of the SH1 Papakura to Drury project will begin early next month, with the contract awarded to Fulton Hogan
New Zealand releases revised PPP framework
24 views
New Zealand has refined its Public Private Partnership (PPP) framework to enhance the planning, procurement, and delivery of future infrastructure projects.